Telecommunication Infrastructure Sharing

From 11/05/2020, the process of sharing requests is temporarily suspended to update the excess of remaining fibers. We will reopen the process shortly.

  • All
  • Geração
  • Outros Projetos
  • Transmissão
PATE 1

PATE – Parintins Amazonas Transmissora de Energia

State: Pará e Amazonas
Length:
Tension:
Substations:
SE own:
Trafficking capacity:
Entry of Actual Business Transaction:
Celeo Networks Participation:
SJPD6ENERG_IMG 1

SJP – São João do Piauí

State: Piauí
Length: 16,9 km
Tension: 500 KV
Substations: 2
SE own: 1
Trafficking capacity:
Entry of Actual Business Transaction: 01/2020
Celeo Networks Participation: 100%
DCIM100MEDIADJI_0132.JPG

SITE – Serra de Ibiapaba de Energia

State: Piauí/Ceará
Length: 366 km
Tension: 230/500 KV
Substations: 7
SE own:
Trafficking capacity: 4.200 MVA
Entry of Actual Business Transaction: 02/2020
Celeo Networks Participation: 100%
CAIUA SE Cascavel Norte

Caiuá – Caiuá Transmissora de Energia

State: Paraná
Length: 142 KM
Tension: 230
Substations: 5
SE own: [2]
Trafficking capacity: 700 MVA
Entry of Actual Business Transaction: 10/05/2014 - LT 230 Kv Umuarama/Guaría | 15/07/2014 - LT 230 Kv Cascavel Norte/Cascavel Oeste | 15/07/2014 - SE Cascavel Norte | 23/07/2014 - SE Santa Quitéria
Celeo Networks Participation: 51%
LT CANTE_1 baixa

CANTE – Cantareira Transmissora de Energia

State: Minas Gerais/São Paulo
Length: 342 KM
Tension: 500kV
Substations: 2
SE own:
Trafficking capacity:
Entry of Actual Business Transaction: 03/02/2018 - LT 500 Kv Estreito/Fernão Dias CD
Celeo Networks Participation: 51%
JTE_1_baixa

JTE – Jauru Transmissora de Energia

State: Mato Grosso/Rondônia
Length: 940 KM
Tension: 230kV
Substations: 6
SE own:
Trafficking capacity: -
Entry of Actual Business Transaction: Trecho sul: 23/10/2009 - LT 230 Kv Vilhena/Jauru | Trecho norte: 21/12/2012 - LT 230 Kv Pimenta Bueno/Vilhena | 14/02/2013 - LT 230 Kv Ariquemes/Ji-Paraná | 23/01/2013 - LT 230 Kv Ji-Paraná/Pimenta Bueno | 30/01/2013 - LT 230 Kv Samule/Ariquemes
Celeo Networks Participation: 100%
BTE

BTE – Brilhante Transmissora de Energia

State: Mato Grosso do Sul
Length: 581 KM
Tension: 230/138kV
Substations: 10
SE own: [4]
Trafficking capacity: 300 MVA
Entry of Actual Business Transaction: 12/11/2010 - LT 230 Kv/Imbirussu/Sidrolândia/Anastácio e SE's | 26/08/2012 - LT 230 Kv Chapadão/Imbirussu | 28/01/2011 - SE 230/138 Kv - Ivinhema | 16/11/2010 - SE 230/138 Kv Rio Brilhante; SE 138 Kv Santa Luzia II e LT's 138 KV | 24/02/2011 - Compensador Estático - SE Imbirussu
Celeo Networks Participation: 50%
LT IMTE

IMTE – Integração Maranhense Transmissora de Energia

State: Maranhão
Length: 365 KM
Tension: 500kV
Substations: 2
SE own:
Trafficking capacity: -
Entry of Actual Business Transaction: 02/12/2014 - LT 500 Kv Açailândia/Miranda II
Celeo Networks Participation: 51%
LTC_3

LTC – Linhas de Transmissão Corumbá

State: Mato Grosso do Sul
Length: 279 KM
Tension: 230kV
Substations: 2
SE own: [1]
Trafficking capacity: 200 MVA
Entry of Actual Business Transaction: 30/09/2013 - LT 230 Kv Anastácio - Corumbá CD; SE 238/138 Kv Corumbá
Celeo Networks Participation: 100%
ENTE_1 baixa-min

ENTE – Encruzo Novo Transmissora de Energia

State: Maranhão
Length: 220 KM
Tension: 230kV
Substations: 2
SE own: [1]
Trafficking capacity: 200 MVA
Entry of Actual Business Transaction: 02/07/2012 - LT 230 Kv Miranda - Encruzo Novo; SE 230/69 Kv - Encruzo Novo | 31/08/2015 - Refuerzo SE Encruzo Novo
Celeo Networks Participation: 100%
DCIM100MEDIADJI_0011.JPG

PTE – Pedras Transmissora de Energia

State: Rio de Janeiro
Length: -
Tension:
Substations: 1
SE own: [1]
Trafficking capacity: 1.200 MVA
Entry of Actual Business Transaction: 05/12/2010 - SE 345/138 Kv - Venda das Pedras
Celeo Networks Participation: 100%
IMG-20190415-WA0033

CTE – Coqueiros Transmissora de Energia

State: Goiás
Length: 65 km
Tension: 500/230 kV
Substations: 3
SE own: [2]
Trafficking capacity: 675 MVA
Entry of Actual Business Transaction: 16/01/2010 - LT 500 Kv São Simão - Itaguaçu; SE 500/230 Kv - Itaguaçu; SE 230 Kv - Barra dos Coqueiros
Celeo Networks Participation: 100%
LTT_1

LTT – Linhas de Transmissão Triângulo

State: Minas Gerais
Length: 695 km
Tension: 500 kV
Substations: 6
SE own: [1]
Trafficking capacity: 1.800 MVA
Entry of Actual Business Transaction: 27/12/2008 - SE 500/345 Kv - Estreito e LT 50 Kv Nova Ponte C2/Estreito | 10/02/2009 - LT 500 Kv Nova Ponte C2/Emborcação (um mês antes da data contratual) | 27/11/2008 - LT 500 Kv Itumbiara/Nova Ponte e São Gotardo2/Bom Despacho 3 C2 | 28/11/2008 - LT 500 Kv São Gotardo/Nova Ponte
Celeo Networks Participation: 100%
FB_IMG_1557235565557

VCTE – Vila do Conde Transmissora de Energia

State: Pará
Length: 324 km
Tension: 500 kV
Substations: 2
SE own:
Trafficking capacity: -
Entry of Actual Business Transaction: 09/05/2006 - LT 500 KV Tucuruí - Vila do Conde
Celeo Networks Participation: 100%

SYSTEM OPERATION CENTER - COS

Celeo Redes Brasil’s concession facilities are supervised and remotely controlled from System Operational Center - COS-Celeo Redes Brasil, placed in Rio de Janeiro, which is integrated with National Electric System Operator-ONS and other agents. Real-time operation of COS-Celeo Redes Brasil is performed in 24-hour continuous-shift, consisting of skilled and certified operators in accordance with ONS Network Procedures. Corporate responsibility.

PRECISA DE AJUDA?
ENTRE EM CONTATO COM A GENTE
FALE CONOSCO